Wednesday, November 3, 2010

Alternate Solution 3


This solution is designed with respect to the third set of specifications and limitations marketed toward small boat users.  This set requires the marina to meet the needs of 150 wet slip berthing areas and small boat ramp users while containing the marina within the specified grounds.  The marina is responsible for providing necessary facilities, including general parking, ramp user parking, a boat ramp to be used by boats up to 24 feet in length, restrooms, fuel storage, vessel maintenance and repair area, a café, and the harbormaster’s office.  Separate buildings house the vessel repair, and bathroom facilities.  The café and harbormaster’s office are to use one building jointly.  These three buildings are each 30’ x 50’.  The fuel storage area is only a specified 40’ x 60’ area to be designed by the Civil Fuel Storage/Pump Engineer.   

This plan boasts one main entrance to be used by all users.  The entrance is located along Hartshorne Drive, 50 feet north of the bend in the road.  The entrance leads to a two-way road that directs the user’s attention towards the focal point of the marina – the main circular dock.  Upon entering through this entrance into the marina, users are able to immediately  turn north into the vessel maintenance repair and fuel area, or travel further west towards to the dock.  Upon the end of the road, users can turn right into the non ramp user’s parking lot or left to access the ramp and ramp parking.  Ramp users are able to launch their boats from the ramp, and park their cars with attached trailers efficiently within a reasonable amount of proximity.  There is an exit behind the ramp staging area for ramp users that have picked up their boats and wish to leave without traveling through a busy parking lot.  With this design the flow of traffic is directed generally in two counter clockwise circles that meet at the entrance of the marina.  Maintaining one entrance while separating ramp users from non-ramp users will increase ease of use and efficiency.       

The general parking lot is a one-way parking lot providing.  It provides one entrance and one exit.  The trailer parking consists of four one-way aisles directed towards the lot exit.  It provides 28 40’ x 13’ stalls.

The ramp area located on the southern most tip of the site along with the fuel storage and vessel maintenance areas are paved in with an impervious surface. 

The two buildings located just east of the focal point will house restroom facilities, the café and harbormasters office.  They are each 50’ x 30’.  These buildings are surrounded by a triangular area of greenery.  The greenery is surrounded by a side walk providing entrances to each building, the focal point, and the general parking lot.             